| date | Project progress | photo |
|---|---|---|
| 2025-09-20 | the roof of the seventh floor is completed | ![]() |
| 2025-08-18 | the roof of the fifth floor is completed | ![]() |
| 2025-07-08 | the roof of the third floor is completed | ![]() |
| 2025-06-04 | first floor roof inspection | ![]() |
| 2025-05-12 | inspection of the roof of the first underground floor | ![]() |
| 2025-04-07 | inspection of the roof of the Second underground floor | ![]() |
| 2024-09-20 | Construction begins and excavated | ![]() |